Build update
This video shows the progress to date on the build. In it you can see members of the project team on the roof on a recent site visit. Much of the external work is complete and patient areas such as bedrooms and bathrooms are getting their final fit.
Follow us on social
#NTCFife
Topping out
An important milestone has been reached in the construction of the new National Treatment Centre for orthopaedics at the Victoria Hospital, with a topping out ceremony marking the completion of the highest point of the build. The frame of the construction has now been completed and work continues to clad the exterior to make the build watertight and enable the interior fittings and first-fix electrical works to commence. Watch the video below to learn more about the significance of this milestone as the project nears it's target completion date for later this year.
Timeline
January 2019
Initial agreement approved
2019
External partners procured
October 2019
Outline business case submitted
May 2020
Outline business case approved
October 2020
Full business case submitted
November 2020
Planning consent
December 2020
Full business case approve
January 2021
Planning and Building approval from Fife Council
February 2021
Car parks complete
March 2021
Construction start
Winter 2022
Construction completion