Planned work to replace hot water pipes at Victoria Hospital will begin onsite from next week (w/c 19th June).

The programme is expected to take 18 months to complete, with a phased approach taken to avoid disruption to patients, visitors and services.

The initial phase of the programme will involve the placement of scaffolding to the south of Phase 3. As a result, a section of Car Park D will be closed for an extended period.

Alternative parking is available at Car Park C and Car Park A, with drop-off parking also nearby. 